WORK on improving the Hibiscus Avenue drainage system and road conditions in Honiara is now underway.
This is to provide an alternative route to alleviate traffic congestion along the main highway from Town Ground section to West Honiara.
The Ministry of Infrastructure Development’s (MID) Transport Infrastructure Management Services Division has engaged local contractors to carry out the task.
“The drainage works is to repair the existing drainage system and clearing those that are clog with debris.
“Road relief works continue as well since this strip is a crucial access route to key government buildings and Honiara’s business district,” the division said.
Local supervisors are on-site to oversee the drainage works.
In parallel, work continues on the main highway under the Land and Maritime Connectivity Project (LMCP). China Civil Engineering Construction Corporation (CCECC) is scheduled to begin laying asphalt by April 2025.
This extensive upgrade will expand the road from a two-lane to a four-lane configuration, enhancing accessibility and efficiency for commuters.
The project section spanning from Townground Roundabout to White River bridge is projected for completion by December 2025.
MID acknowledges the patience and understanding of West Honiara community members during this period of construction.
– MID